Timeline:
  • November 24th = deadline for almost final prototype!
  • BY November 13th, finalize all materials that we want for our project and for the Nicaragua group to make it; also have buckets ready for use
  • Be ready for test run by the end of Tuesday the 17th (so that we can do test run on the 20th and make minor modifications)
  • Be totally done by end of class on the 20th
  • Make time for blog (at least 15-20 minutes at the end of every class)
  • Email Lyndsay by Friday (the 13th) with update on overall status of project


Pride/Pain Points (as of November 10, 2015)
  • Pride: Pretty much functioned the way we expected (need to make modifications, but these were modifications we anticipated having to make for prototype #2)
  • Pride: Low-cost! Low-time commitment!
  • Pain: Faucet leaking - faucet was small (as in, didn't allow much water flow), we need to figure out a better way to attach it to the bucket because the little holes where the screws went caused some leaks
  • Pain: Bottom of bucket is hard to take off (we think this will be a persistent issue and something we don't want to change)